Case Brief: M/s. A.P.S. Kushwaha v Municipal Corporation, Gwalior and Ors.

FACTS:
The appellant filed an application under section 11(6) of the Arbitration and Conciliation Act, 1996 before the Madhya Pradesh High Court alleging that on execution of an agreement a work order was issued to him by the respondent and as the bills submitted by the appellant were not paid, it filed a writ petition and that petition was disposed of with a direction to seek reference to arbitration; as the clause 29 of the General Rules and directions for the Guidance of the contractor provided for settlement of disputes by arbitration therefore the appellant requested the Chief Justice to appoint an independent arbitrator to arbitrate upon the disputes. The designate of the Chief Justice appointed a retired Judge of the High Court as arbitrator.
Before   the   Arbitrator,   the   appellant   made   claims   aggregating   to Rs.76,64,725 with interest at 18% per annum. The respondents contested the claims contended that the appellant was not entitled to payment of any of the bills. The arbitrator made an award directing the respondents to pay a sum of Rs.76,64,725 to the appellant with interest at 9% per annum from the date of the award till date of payment.
The respondents then filed an application under section 34 of the Act for setting aside the award. In the said proceedings, the respondents made an application raising a preliminary objection that the sole arbitrator had no jurisdiction as the dispute had to be decided by arbitration under the Madhya Pradesh Madhyastham Adhikaran   Adhiniyam, 1983. The District Judge, Gwalior before whom the said application was filed rejected the said preliminary objection. The review petition filed by the respondents seeking review of order was also dismissed by the learned District Judge, Gwalior.
Meanwhile, the appellant also filed a review application seeking review of the order by which the designate of the   Chief Justice allowed the application. The said review petition was dismissed by the High Court. The respondent   challenged the arbitral award before the High Court in an arbitration appeal. The High Court allowed the appeal holding that the arbitral award passed by the sole arbitrator was without jurisdiction.
Feeling aggrieved, the appellant has challenged the orders of the Madhya Pradesh High Court.
ISSUE FOR CONSIDERATION:
Whether there was inherent lack of jurisdiction in the Arbitrator, thereby nullifying the award?
HELD:
The apex Court allowed the appeals. The Court observed that as per V.A.Tech Escher Wyass Flovel Ltd. vs. M.P. S.E.Board, the provisions of the Act would apply where there was an Arbitration clause and the provisions of the 1983 Adhiniyam would apply where there was no Arbitration clause. In this case, it said, it is not in dispute that the contract between the parties contained an arbitration clause (clause 29). Further, in SBP & Co. v. Patel Engineering Ltd., it was held that once the Chief Justice or his designate appoints an Arbitrator after satisfying himself that the   conditions for exercise of power to appoint an arbitrator   are   present,   the   arbitral   tribunal   could   not   go   behind such   decision   and   rule   on   its   own   jurisdiction   or   on   the   existence   of   an arbitration   clause.   Therefore   the   contention   of   the   respondents   that   the arbitrator ought to have considered the objection relating to jurisdiction and held that he did not have jurisdiction, cannot be accepted.

Leave a Reply

Your email address will not be published. Required fields are marked *